Sindh Phase - II Major Irrigation Project JI00993

From
Jump to: navigation, search
« Go Back
Salient Features
#AttributeValue
1Irrigation Project NameSindh Phase - II Major Irrigation Project
2Irrigation Project Name Alias
3PurposeIrrigation
4TypeMajor
5Engineering TypeDiversion, Storage
6StatusOngoing
7StateMadhya Pradesh
8Districts BenefitedShivpuri,Datia,Bhind,Gwalior
9BasinGanga
10RiverParwati,Sindh
11Project SharingNone
12IntercountryNone
13InterbasinNo
14Work Started in 5 Year PlanAPAndhra Pradesh (1978-80)
15Completed in 5 Year Plan
16Project Approval StatusPlanning Commission
17Year of Approval by Planning Commission1998
18Approved Cost (Rs. in cr)510.94
19Actual Cost (Rs. in cr)
20Culturable Command Area (CCA) (th ha)98.25
21Ultimate Irrigation Potential (UIP) (th ha)162
22Potential Created (PC) (th ha)
23Project Covered under ERM SchemeNo
24Project Covered under CADA SchemeNo
25Project Covered under AIBP SchemeYes
26Studies Conducted
27Project Covered under Tribal Sub-PlanNo
28Project Covered under Drought Prone Area Programme (DPAP)Yes
29Remarks

Associated Entities with Irrigation Project
#NameType
1Harsi DamDam
2Madikheda (Mohini Sagar ) DamDam
3Mohini Pickup WeirDam
4Samoha WeirBarrage/ Weir/ Anicut (BWA)
5Ukalia AnicutBarrage/ Weir/ Anicut (BWA)
Explore in Water Resources Projects Sub Info. System

Project Description

The project situated in Shivpuri district of Madhya Pradesh across river Sindh, is a multipurpose project which envisages construction of following components:

  1. Madikheda Dam (Mohini Sagar dam). 1072 meter long composite masonry cum earthen dam across river Sindh with Gross storage of 901.80 Mcum and live storage capacity of 834.83 Mcum. 218.50 long gated ogee type spillway with capacity of 14026.40 cumec. Spillway gates 23 numbers of size 12.497X9.85 meter.
  2. Modernisation of Mohini Pick up Weir including installation of gates. 2number of gates of size 4.87x9.85 meter on the creast of existing Mohini pickup weir to impound additional storage of 89.20 Mcum.
  3. Right bank high-level Ukaila canal.
  4. Right bank canal up to Mahuar River.
  5. Samoha Pickup Weir & R.B.C beyond Mahuar River.
  6. Extension of left bank Doab canal.
  7. Harsi high-level canal.
  8. Powerhouse with installed capacity of 60 MW at Madikheda Dam.

Sindh Phase - II project was originally framed for an estimated cost of Rs. 185.00 crore (1978) to irrigate an area of 1,62,100 ha (CCA = 98,251 ha with 165% intensity of irrigation). The project with the cost of Rs 510.94 crore (1991-92 price level) (excluding power component) received Investment clearance of Planning Commission vide their letter No: 2(14) 93-ICAD/GoI dated 17.03.1998. The revised estimated cost of the project for Rs 2945.74 crore (2009 price level) received investment clearance of Planning Commission in the year 2010. The project will provide irrigation in districts of Shivpuri, Bhind, Gwalior and datia.

Present Status

The project was started in the year 1978 and the project was brought under AIBP during 1998-99. The Mohini dam is completed in the year 2008. So far upto March 2011 potential of 77254 hectare is created. Total Expenditure on the project upto march 2012 so far is Rs 1355.769 crore.

Madhikheda dam(Sindh phase II project) year 2000.jpg
Sindh Phase II Map.jpg
Personal tools
Namespaces
Variants
Actions
Navigation
Topics
Toolbox

Either scripts and active content are not permitted to run or Adobe Flash Player version 10.0.0 or greater is not installed.

Get Adobe Flash Player