Kallada Major Irrigation Project JI02687

From
Jump to: navigation, search
« Go Back
Salient Features
#AttributeValue
1Irrigation Project NameKallada Major Irrigation Project
2Irrigation Project Name Alias
3PurposeIrrigation
4TypeMajor
5Engineering TypeDiversion, Storage
6StatusCompleted
7StateKerala
8Districts BenefitedAlappuzha,Thiruvananthapuram,Pathanamthitta,Kollam
9BasinWest flowing rivers from Tadri to Kanyakumari
10RiverKallada
11Project SharingNone
12IntercountryNone
13InterbasinNo
14Work Started in 5 Year PlanIII-Plan
15Completed in 5 Year PlanX-Plan
16Project Approval StatusPlanning Commission
17Year of Approval by Planning Commission1966
18Approved Cost (Rs. in cr)13.28
19Actual Cost (Rs. in cr)653.67
20Culturable Command Area (CCA) (th ha)53.514
21Ultimate Irrigation Potential (UIP) (th ha)92.8
22Potential Created (PC) (th ha)80.579
23Project Covered under ERM SchemeNo
24Project Covered under CADA SchemeYes
25Project Covered under AIBP SchemeYes
26Studies Conducted
27Project Covered under Tribal Sub-PlanNo
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks

Associated Entities with Irrigation Project
#NameType
1Kallada (Parappar) (Id) DamDam
2Ottakkal BarrageBarrage/ Weir/ Anicut (BWA)

Explore in Water Resources Projects Sub Info. System

Project in Brief

Kallada irrigation and Tree crop Development project is the largest irrigation project in Kerala. The command area of this project is distributed over Kollam, Pathanamthitta and Alappuzha district and coveres Pathanapuram, Kottarakkara, Kollam, Kunnathur, Karunagappally, Adoor, Mavelikkara and Karthikappally Taluks. The project was planned to irrigate net cultivable command area of 61630 Ha. During the course of execution few canals including Kayamkulam Branch canal were dropped and now this project is benefited for a net cultivable command area of 53514 Ha in 92 villages. Head works is completed during 1986. Left and right bank main canals are fully completed. Right bank main canal partially commissioned during 1986 and left bank main canal during 1992.

Main components of the project:

1. Dam at Parappar:- Reservoir is formed by constructing a gravity type masonry dam across Kallada river at Parappar near Thenmala and a saddle earthen dam at Pallamvetty. Gross storage capacity of the reservoir is 504.92 Mm3.

2. Pick up weir at Ottackal : A pick up weir just 5 Km down stream of dam is provided at Ottakkal. This has got a capacity of 17 Mm 3. The main canals (RBC and LBC) off take from the weir. The tail race water from the power house provided just at the downstream of the dam is collected at weir and used for Irrigation. When there is no power generation, the irrigation valves are opened and water collected at Ottackal.

Kallada.jpg

Command Area Map

Kallada .jpg